Recently, a client with a 6-acre property in Hilo asked me a question I didn’t immediately know the answer to: Can I build a vehicle bridge across a stream that runs through my land? The stream—Waiākea Stream—is dry most of the time but swells during heavy rains.

Curious and wanting to give a clear answer, I did some research. Here’s what I found, and what any Big Island landowner should know if you’re thinking about crossing a stream on your property.

A common solution is building a bridge or installing a culvert, but this requires several permits and approvals. Here’s a friendly, straightforward guide to navigating this process:

1. State Permits (SCAP)

Hawaiʻi requires a Stream Channel Alteration Permit (SCAP) whenever you plan work within or over a stream (even a dry one!). You’ll apply through the Department of Land & Natural Resources (DLNR), specifically their Commission on Water Resource Management (CWRM).

You’ll need to provide:

2. Federal Permits (U.S. Army Corp of Engineers)

Streams often fall under federal protection, which means you’ll likely need approval from the U.S. Army Corps of Engineers. Luckily, smaller projects often qualify for faster approvals under something called a Nationwide Permit, simplifying your application if the project won’t significantly impact the environment.

Just submit a simple notification to the Corps, and they’ll let you know if you qualify or need a more thorough review. 📩

3. County Permits

Hawaiʻi County must also approve your plans, primarily to ensure safety and compliance with local building codes. They’ll look at:

  • Stability and proper sizing of the bridge or culvert
  • Flood control measures
  • Potential impacts on neighboring properties

Working closely with Hawaiʻi County’s Public Works department can greatly speed up your approval process. 🤝

4. Engineering & Environmental Considerations

Hilo experiences heavy rainfall, so your crossing must handle significant water flow to prevent washouts or flooding. Hiring an engineer is crucial—they’ll help:

  • Determine the best type of crossing (bridge or culvert)
  • Design it to withstand heavy rains and occasional flooding
  • Include erosion and sediment control to protect your property and surrounding environment

The Approval Process Step-by-Step

  • Hire Professionals: Engage an engineer and possibly an environmental consultant.
  • Prepare Plans: Clear, professional plans showcasing the crossing and environmental safeguards.
  • Submit Applications: Apply for state (SCAP), federal (Army Corps), and county permits.
  • Approval Period: Allow some review time—usually several months.
  • Start Construction: Once approved, build according to your approved plans and conditions.

Special Note for Conservation Land

If your property is in a State Conservation District, the process becomes more complex. In addition to the permits listed above, you’ll need to apply for a Conservation District Use Permit (CDUP) from DLNR’s Office of Conservation and Coastal Lands (OCCL). This permit includes stricter guidelines and a more detailed review process. It’s essential to verify your land’s zoning designation early on to avoid delays.

Is It Allowed?

Absolutely! Building bridges or culverts is allowed as long as you follow the permitting processes, ensure proper design, and minimize environmental impacts.

Tips for Landowners

  • Start early, as permits take time.
  • Consult an engineer experienced with local conditions.
  • Keep neighbors informed—they might be affected or interested.
  • Plan for future maintenance and flood control needs.

By understanding this process upfront, you’ll be well-prepared to bridge that seasonal stream and fully enjoy your property.

This is why the permits matter.

The very same week I was researching this topic, the Hawaiʻi Department of Health announced they had caught and fined a landowner for building an illegal stream crossing in Waiheʻe Stream.

Not only did the crossing cause environmental damage, but the penalties were serious—proving that “just doing it” without approval is a huge risk.

🔗 Read the full notice here

Disclaimer

I’m not an engineer or a permitting specialist, but I’ve done my best to outline the basic process based on available public information. For the most accurate and up-to-date guidance, be sure to consult the appropriate agencies and professionals directly.

About Me

I’m Dan Tousignant, Principal Broker of Living on Big Island Realty, certified home inspector, property manager, landlord and Hawaiʻi registered agent. With extensive experience in construction, real estate investing, and business management, as well as experience living off-grid both abroad and here on the Big Island, I provide clients with practical, real-world guidance through the Big Island’s unique real estate and business landscape. I am also the author of Moving to Big Island: Life on the Eastside. Whether you’re buying or selling a home, need a thorough inspection, or are setting up a business, I’m here to help. Reach out anytime at dan@livingonbigisland.com.